Hatch to build transmission line

  • Published: 19/08/2008
Image1

HATCH Energy will establish a transmission line to provide power to the Prosperity Mine in British Columbia.

The company will engineer the 125km, 230kV transmission line. It will also provide cost estimates to determine long-term development possibilities.

Basic engineering is scheduled to be completed by early September 2008, with the transmission line to be in service by mid-2010.

Hatch Energy offices in Winnipeg, Castlegar, and Oakville are undertaking the project.